{"id":7947,"date":"2026-07-24T11:44:54","date_gmt":"2026-07-24T08:44:54","guid":{"rendered":"https:\/\/axinar.com\/?p=7947"},"modified":"2026-07-24T11:44:54","modified_gmt":"2026-07-24T08:44:54","slug":"solar-carport-permit-greece","status":"publish","type":"post","link":"https:\/\/axinar.com\/en\/blog\/solar-carport-permit-greece","title":{"rendered":"Solar Carport Permitting in Greece: Process, Legislation, Timeline"},"content":{"rendered":"<p>Permitting of photovoltaics in Greece was historically one of the most complex parts of installation. For <strong>solar carport<\/strong> specifically, the situation has simplified significantly in recent years, but critical points still exist that determine whether the project will complete in 1 month or 6 months.<\/p>\n<div style=\"background:rgba(255,193,7,.12);border-left:4px solid #ffc107;padding:14px 18px;margin:20px 0;border-radius:4px;color:#ffffff;\">\n<strong>Important Disclaimer:<\/strong> PV permitting legislation is frequently updated. The information below is <em>indicative<\/em>. For each specific project, <strong>verify with the local Planning Office, DEDDIE and RAAEY<\/strong> the current limits and process.\n<\/div>\n<h2>Two Parallel Processes<\/h2>\n<p>For each solar carport there are two separate permitting parts:<\/p>\n<ol>\n<li><strong>Building Permit (Structural):<\/strong> For the canopy construction, Planning Office or New Building Code (NOK)<\/li>\n<li><strong>Electrical Connection:<\/strong> For grid connection with DEDDIE + RAAEY (depending on capacity)<\/li>\n<\/ol>\n<h2>1. Building Permit<\/h2>\n<h3>Solar Carport as &#8220;Temporary Construction&#8221;<\/h3>\n<p>The <strong>New Building Code (NOK)<\/strong> provides for the category of temporary constructions that don&#8217;t require a building permit, provided specific limits are observed:<\/p>\n<ul>\n<li>Construction height (typically up to 3\u20133.5m)<\/li>\n<li>Area (typically up to 40m\u00b2 for residences)<\/li>\n<li>Distance from plot boundaries<\/li>\n<li>Plot coverage (must not exceed allowed)<\/li>\n<\/ul>\n<p>AXINAR notes in the technical dossier of the solar carport that <strong>up to 40m\u00b2 a building permit is typically not required<\/strong>. This depends on building coefficients of the specific area, <strong>ask the local Planning Office<\/strong>.<\/p>\n<h3>Small Scale Permit (AMK)<\/h3>\n<p>If you exceed the limits but are under some smaller threshold, you need a <strong>Small Scale Permit<\/strong>, simpler and faster than a full building permit. Typically:<\/p>\n<ul>\n<li>Submission to Planning Office with drawings from architect or civil engineer<\/li>\n<li>Approval timeline: 15\u201345 days<\/li>\n<li>Approval cost: low (typically &lt; 500\u20ac)<\/li>\n<\/ul>\n<h3>Full Building Permit<\/h3>\n<p>For large solar carports (commercial spaces, industrial parking), approval time 3\u20136 months, higher cost and documentation.<\/p>\n<h2>2. Electrical Connection<\/h2>\n<h3>Net Metering<\/h3>\n<p>Net metering allows connection of the PV system to the grid and transfer of produced energy:<\/p>\n<ul>\n<li><strong>Capacity up to 10.8 kVA:<\/strong> Simplified process through DEDDIE (typically ~1\u20132 months)<\/li>\n<li><strong>Larger capacity:<\/strong> Requires more documentation, role of RAAEY<\/li>\n<\/ul>\n<h3>Self-Consumption Without Grid (Off-Grid)<\/h3>\n<p>If solar carport connects only to EV charger or battery storage <strong>without grid connection<\/strong>, the process simplifies dramatically, no DEDDIE needed, only typical electrical installation.<\/p>\n<h2>Typical Project Timeline<\/h2>\n<table>\n<thead>\n<tr>\n<th>Phase<\/th>\n<th>Time<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td>System selection + static study (AXINAR free)<\/td>\n<td>1\u20132 weeks<\/td>\n<\/tr>\n<tr>\n<td>Building permit (if needed)<\/td>\n<td>0\u201345 days<\/td>\n<\/tr>\n<tr>\n<td>DEDDIE application (if grid-connected)<\/td>\n<td>1\u20132 months<\/td>\n<\/tr>\n<tr>\n<td>Construction + PV installation<\/td>\n<td>1\u20133 weeks<\/td>\n<\/tr>\n<tr>\n<td>Grid connection + activation<\/td>\n<td>2\u20134 weeks<\/td>\n<\/tr>\n<tr>\n<td><strong>Total (typically)<\/strong><\/td>\n<td><strong>2\u20134 months<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h2>Practical Tips for Faster Permitting<\/h2>\n<ul>\n<li><strong>Prefer \u2264 40m\u00b2:<\/strong> If possible, design a carport that doesn&#8217;t require building permit<\/li>\n<li><strong>Good pre-study:<\/strong> Detailed static study + electrical drawings save time on objections<\/li>\n<li><strong>Start DEDDIE early:<\/strong> Electrical connection is usually the slowest part, submit application before construction begins<\/li>\n<li><strong>Professional installer:<\/strong> Certified electrician for electrical study, avoids drawing returns<\/li>\n<\/ul>\n<h2>Indicative Legislative Framework<\/h2>\n<p><em>(Verify for current status at each point in time)<\/em><\/p>\n<ul>\n<li><strong>Law 4685\/2020:<\/strong> Modernization of Environmental Legislation, RES permitting procedures<\/li>\n<li><strong>New Building Code (NOK):<\/strong> Temporary constructions, coverage, building coefficients<\/li>\n<li><strong>Law 4964\/2022:<\/strong> Energy market &amp; net metering &amp; RES<\/li>\n<li><strong>RAAEY Regulatory Acts:<\/strong> For larger installations<\/li>\n<li><strong>DEDDIE Guidelines:<\/strong> For electrical connection<\/li>\n<\/ul>\n<div style=\"border:1px solid rgba(221,43,28,.28);border-radius:10px;padding:22px;margin:26px 0;background:rgba(255,255,255,.02);\">\n<div style=\"margin-bottom:14px;\">\n<div style=\"font-family:'Barlow Condensed', sans-serif;font-size:1.35rem;font-weight:700;line-height:1.15;margin-bottom:2px;color:#ffffff;\">AXINAR Solar Carport<\/div>\n<div style=\"opacity:.85;font-size:.92rem;color:#ffffff;\">Free static study, ready for permitting<\/div>\n<\/div>\n<div>\n<p style=\"margin:0 0 12px 0;line-height:1.55;color:#ffffff;\">AXINAR provides complete technical documentation for permitting: static study, electrical drawings, CE conformity declarations.<\/p>\n<ul style=\"margin:0 0 14px 0;padding-left:20px;color:#ffffff;\">\n<li style=\"margin-bottom:6px;\">Steel S420GD, Eurocode 1 design<\/li>\n<li style=\"margin-bottom:6px;\">Bifacial PERC panels<\/li>\n<li style=\"margin-bottom:6px;\">Free static study for permit<\/li>\n<\/ul>\n<p><a href=\"\/en\/solar-panel-mounts\/solar-carport\" style=\"display:inline-block !important;background:#dd2b1c !important;color:#ffffff !important;font-family:Barlow Condensed, sans-serif !important;font-size:.9rem !important;font-weight:700 !important;text-transform:uppercase !important;letter-spacing:1.2px !important;padding:10px 22px !important;border-radius:6px !important;text-decoration:none !important;margin-top:10px;\">See the product \u2192<\/a><\/div>\n<\/div>\n<h2>Request a Static Study &amp; Quote<\/h2>\n<p>Send us your project basics, square meters, roof or ground type, zone, PV capacity, and we&#8217;ll respond within 24 hours with a recommended mounting system and <strong>free static study<\/strong>.<\/p>\n<p><a href=\"\/en\/contact\" style=\"display:inline-block !important;background:#dd2b1c !important;color:#ffffff !important;font-family:Barlow Condensed, sans-serif !important;font-size:1rem !important;font-weight:700 !important;text-transform:uppercase !important;letter-spacing:1.5px !important;padding:12px 28px !important;border-radius:8px !important;text-decoration:none !important;margin-top:8px;\">Request quote \u2192<\/a><\/p>\n<hr>\n<p><em>See <a href=\"\/en\/blog\/solar-carport-ev-charger\">Solar Carport with EV charger<\/a>.<\/em><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Permitting of photovoltaics in Greece was historically one of the most complex parts of installation. For solar carport specifically, the [&hellip;]<\/p>\n","protected":false},"author":16,"featured_media":4058,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_eb_attr":"","site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"rank_math_title":"Solar Carport Permit Greece: Process Guide | AXINAR","rank_math_description":"Complete guide to solar carport permitting: limits without building permit, DEDDIE connection, legislation (Law 4685\/2020, NOK), installation timeline.","footnotes":""},"categories":[176],"tags":[],"class_list":["post-7947","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog"],"_links":{"self":[{"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/posts\/7947","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/users\/16"}],"replies":[{"embeddable":true,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/comments?post=7947"}],"version-history":[{"count":0,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/posts\/7947\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/media\/4058"}],"wp:attachment":[{"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/media?parent=7947"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/categories?post=7947"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/axinar.com\/en\/wp-json\/wp\/v2\/tags?post=7947"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}